Our works are now complete on the new 110 kV OHL from Brockaghboy Windfarm to Garvagh Main Substation Project. Our full scope of works entailed the construction & installation of 7nr H Pole Foundations, 4nr Pad & Column Foundations and installation of 2.2km of temporary access roads. In Quarter 1 2022, Power Grid Civils Ltd also completed the full reinstatement of all site works and installation of permanent fencing & gates.